As Promised, This Is The Complete Expenditure Breakdown Of N162.5b SUKUK Funds Released For 44 Critical Road Projects Across The Nation's Six Geo-Political Zones. The Intention Behind Delivering This Breakdown Is To Offer Insight For Public Accountability. @TrackaNG

#LONGThread
Zonal Breakdown:

North-Central:
N26.5bn (2020)
143.44 kms (2020)
8 Roads

North-East:
N30.5bn
277.53 kms
8 Roads

North-West:
N26.5bn
227.47 kms
7 Roads

South-West:
N27bn
59.74 kms
6 Roads

South-East:
N26bn
99.45 kms
5 Roads

South-South:
N26bn
121.78 kms
10 Roads
NORTH-CENTRAL BREAKDOWN: EIGHT ROADS

(1) DUALIZATION OF SULEJA-MINNA ROAD PHASE II (KM 40+000 - 101+000) IN NIGER STATE

Contractor: Salini Nigeria Ltd
Contract Sum: N36.2bn
Current Completion Level: 17.20%
2020 SUKUK Payment: N2.5bn
Road/Bridge Works
Kms Covered (2020): 14km
(2) ABUJA-ABAJI ROAD (SECTION 1: INTERNATIONAL
AIRPORT LINK ROAD JCT - SHEDA VILLAGE JCT)

Contractor: Dantata & Sawoe
Contract Sum: N28.6bn
Current Completion Level: 96.11%
2020 SUKUK Payment: N1.0bn
PROJECT COMPLETION
Kms Covered (2020): 2.2km
(3) ABUJA-LOKOJA ROAD: SECTION IV (KOTON KARFE - LOKOJA)

Contractor: Gitto Construction
Contract Sum: N31.08bn
Current Completion Level: 76.0%
2020 SUKUK Payment: N2.5bn
Asphalt Wearing and 1st & 2nd Coat surface dressing on shoulders with lined drains
Kms Covered (2020): 5.5km
(4) DUALIZATION OF OBAJANA JUNCTION TO BENIN
PHASE 2: SECTION 1 (OBAJANA JUNCTION TO OKENE)

Contractor: CGC Nigeria Ltd
Contract Sum: N30.56bn
Current Completion Level: 32.66%
2020 SUKUK Payment: N3.5bn
Ongoing Dualization works
Kms Covered (2020): 63.05km
(5) CONSTRUCTION OF OJU/LOKO-OWETO BRIDGE TO
LINK BENUE & NASARAWA WITH NEW APPROACH ROADS

Contractor: RCC Nigeria Ltd
Contract Sum: N51.61bn
Current Completion Level: 96.7%
2020 SUKUK Payment: N6.0bn
PROJECT COMPLETION
Kms Covered (2020): 5.0km
(6) RECONSTRUCTION OF BIDA-LAPAI-LAMBATA ROAD IN
NIGER STATE

Contractor: CGC Nigeria Ltd
Contract Sum: N33.3bn
Current Completion Level: 13.06%
2020 SUKUK Payment: N5.0bn
CH25+000 - CH35+500, CH43+600 - CH55+000 up to A/C Wearing Course
Kms Covered (2020): 20.9km
(7) RECONSTRUCTION OF MAKURDI-NAKA-ADOKA-ANKPA ROAD IN BENUE STATE

Contractor: Gilmor Engineering
Contract Sum: N27bn
Current Completion Level: 0.53%
2020 SUKUK Payment: N3.0bn
CH70+500 - CH58 (12.5Km), CH70+650 - CH150 (12.5Km) up to A/C Binder Course
Kms Covered (2020): 25.0km
(8) CONSTRUCTION OF ROAD LINKING BARO PORT TO GULU TOWN IN NIGER STATE

Contractor: GR Building Nigeria
Contract Sum: N10.61bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N3.0bn
PROJECT COMMENCEMENT
Kms Covered (2020): 7.75km
NORTH-EAST BREAKDOWN: EIGHT ROADS

(1) KANO-MAIDUGURI ROAD: (SECTION II - SHUARI LINK TO AZARE)

Contractor: Setraco Nigeria Ltd
Contract Sum: N65.31bn
Current Completion Level: 86.62%
2020 SUKUK Payment: N11.0bn
Ongoing Construction
Kms Covered (2020): 53.93km
(2) KANO-MAIDUGURI ROAD: (SECTION III - AZARE LINK TO POTISKUM)

Contractor: Mothercat Ltd
Contract Sum: N45.18bn
Current Completion Level: 91.79%
2020 SUKUK Payment: N2.0bn
PROJECT COMPLETION
Kms Covered (2020): 0km - Toll Plazas/Weighbridges
(3) KANO-MAIDUGURI ROAD: (SECTION IV - POTISKUM LINK TO DAMATURU)

Contractor: CGC Nigeria Ltd
Contract Sum: N51.90bn
Current Completion Level: 80.51%
2020 SUKUK Payment: N4.0bn
Main Carriageway Works
Kms Covered (2020): 94.0km
(4) KANO-MAIDUGURI ROAD: (SECTION V - DAMATURU LINK TO MAIDUGURI)

Contractor: CCECC Nigeria Ltd
Contract Sum: N67.79bn
Current Completion Level: 50.94%
2020 SUKUK Payment: N4.0bn
Main Carriageway Works
Kms Covered (2020): 59.6km
(5) REHABILITATION OF GWOZA-DAMBOA-GONIRI-NGAMDU IN BORNO STATE

Contractor: Hajaig Construction Nigeria Ltd
Contract Sum: N34.60bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N3.0bn
Site Clearing/Earthworks, Culverts, Pavement & Surfacing
Kms Covered (2020): 15.0km
(6) RECONSTRUCTION OF MAYO BELWA-JADA-GANYE-TOUGO ROAD IN ADAMAWA STATE

Contractor: Triacta Nigeria Ltd
Contract Sum: N22.69bn
Current Completion Level: 14.14%
2020 SUKUK Payment: N3.0bn
Asphalt Wearing & Reconstruction
Kms Covered (2020): 42.0km
(7) CONSTRUCTION OF IBI BRIDGE IN TARABA STATE

Contractor: RCC Nigeria Ltd
Contract Sum: N57.07bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N2.0bn
Piles and Pile caps for Axis 2 & 3, 4 & 5 Ibi Side
Kms Covered (2020): Bridgeworks
(8) REHABILITATION OF NGURU-GASHUA-BAYAMARI
ROAD: SECTION II (GASHUA-BAYAMARI) IN YOBE STATE

Contractor: Ric Roc Construction Ltd
Contract Sum: N11.77bn
Current Completion Level: 0.14%
2020 SUKUK Payment: N1.5bn
Rehabilitation up to Asphalt Binder
Kms Covered (2020): 13.0km
NORTH-WEST BREAKDOWN: SEVEN ROADS

(1) KANO-MAIDUGURI ROAD: (SECTION I – KANO LINK TO WUDIL WITH LINK TO SHUARI)

Contractor: Dantata & Sawoe
Contract Sum: N55.1bn
Current Completion Level: 67.51%
2020 SUKUK Payment: N4.5bn
Interchange 1,2 & Carriageway
Kms Covered (2020): 58.0km
(2) DUALIZATION OF KANO-KATSINA ROAD: (PHASE 1 - KANO TOWN AT DAWANAU ROUNDABOUT TO
KATSINA STATE BORDER) IN KANO STATE

Contractor: CCECC Nigeria Ltd
Contract Sum: N14.0bn
Current Completion Level: 51.48%
2020 SUKUK Payment: N2.75bn
Ongoing Dualization
Kms Covered (2020): 57.0km
(3) CONSTRUCTION OF KADUNA EASTERN BY-PASS

Contractor: Eksiogulari Nigeria Ltd
Contract Sum: N38.19bn
Current Completion Level: 39.40%
2020 SUKUK Payment: N4.0bn
CH16+000 - CH37+000 (Road Works up to A/C Binder Course), Bridgeworks at Chikaji CH35
Kms Covered (2020): 21.0km
(4) CONSTRUCTION OF KANO WESTERN BY-PASS

Contractor: Dantata & Sawoe
Contract Sum: N22.77bn
Current Completion Level: 66.98%
2020 SUKUK Payment: N4.0bn
Asphalt Wearing; Bridgework (3 & 4); CH 0+425 - CH 9+030 Median Drain & Slope Protection (Bridge 2)
Kms Covered (2020): 12.47km
(5) DUALIZATION OF KANO-KATSINA ROAD: (PHASE II - KANO/KATSINA BORDER LINK TO KATSINA
STEEL ROLLING MILLS ROUNDABOUT)

Contractor: CCECC Nigeria Ltd
Contract Sum: N29.65bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N3.75bn
Ongoing Dualization
Kms Covered (2020): 26.5km
(6) REHABILITATION OF SOKOTO-TAMBUWAL-JEGA-KONTAGORA-MAKERA ROAD: (SECTION I - SOKOTO / KEBBI STATES)

Contractor: Triacta Nigeria Ltd
Contract Sum: N30.45bn
Current Completion Level: 68.52%
2020 SUKUK Payment: N5.0bn
Carriageway Reconstruction
Kms Covered (2020): 40.0km
(7) REHABILITATION OF AJINGI-JAHUN-KAFIN HAUSA
ROAD IN JIGAWA STATE

Contractor: H & M Nigeria Ltd
Contract Sum: N25.03bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N2.5bn
Carriageway Reconstruction
Kms Covered (2020): 12.5km

**SECOND THREAD ON SOUTHERN SUKUK ROADS**