NORTH EAST
1. Dualisation of Shuarin-Azare section of Kano–Maiduguri Road linking Kano–Jigawa–Bauchi–Yobe (Section II) (ongoing)

2. Dualisation of Azare–Potiskum section of Kano–Maiduguri Road
linking Kano–Jigawa–Bauchi–Yobe–Borno States. (Section III) (ongoing)

3. Dualisation of Potiskum–Damaturu section of Kano–Maiduguri Road linking Kano–Jigawa–Bauchi–Yobe–Borno States. (Section IV) (ongoing)

4. Dualisation of Damaturu–Maiduguri section of Kano–Maiduguri Road
linking Kano–Jigawa–Bauchi–Yobe–Borno States. (Section V) (ongoing)

5. Reconstruction of Gombe-Numan-Yola Road, ongoing (Gombe-Kaltungo section completed)

6. Reconstruction of 122km Mayo Belwa-Jada-Ganye-Toungo Road, commenced in 2018

7. Construction of 40MW Kashimbila Dam
& Hydro Power Plant, Taraba State (Dam and Power Plant completed; construction of transmission infrastructure to connect the plant to the national grid ongoing)

8. Construction of 29MW Dadin Kowa Hydro Power Plant, Gombe State (ongoing)

9.Completed Takum Water Supply Project,
Taraba State

10. Construction of 3,050MW Mambilla Power Plant,Taraba State ($5.8 billion EPC contract awarded and signed in 2017; negotiations for the financing by the China Exim Bank ongoing)

11. Energizing Education Programme, an initiative of the FGN to provide sustainable
and clean power supply to Federal Universities and University Teaching Hospitals across Nigeria, is being implemented in the Abubakar Tafawa Balewa University–Gubi Campus, Bauchi

12. Transmission Infrastructure (ongoing):

a.330/132KV Molai Transmission Substation in Maiduguri
completed and energized in 2018
b. 330/132KV Damaturu Transmission Substation in Yobe State completed and energized in 2018
c. 60MVA 132/33KV Power Transformers at Bauchi, Bauchi State, added capacity 48MW (2017)
d. 40MVA Mobile Substation at Damboa, Borno State, added capacity
32MW (2017)
e. 28/40MVA Mobile Substation at Mayo Belwa, Adamawa State, added capacity 22.4/32MW (2017)
f. 30/40MVA Mobile Substation at Gombe, Gombe State, added capacity 24MW (2017)

13. Social Investment Programme:
a. 74,000 N-Power Beneficiaries across the six States of
the North East.
b. School Feeding currently ongoing in all 6 States of the North East: Bauchi, Taraba, Borno, Gombe, Yobe and Adamawa

MAJOR ONGOING AND COMPLETED INFRASTRUCTURE PROJECTS BY THE BUHARI ADMINISTRATION
You can follow @kennygee_70.
Tip: mention @twtextapp on a Twitter thread with the keyword “unroll” to get a link to it.

Latest Threads Unrolled: