Inspired by the @10Things_ToKnow about #offshorewind, here are some of mine:
1) it took the UK 11 years to build its first 2GW & 18months to build its last 2
2) Dogger Bank, a proposed project in the North Sea, was once a terrestrial setting during lower sea-level
1) it took the UK 11 years to build its first 2GW & 18months to build its last 2
2) Dogger Bank, a proposed project in the North Sea, was once a terrestrial setting during lower sea-level
3) 41 bombs & explosives were found on Race Bank project, some detonated!
4) Most turbines have an energy payback of less than 6 months and a CO2 payback of 6 months
5) Turbine foundations can be concrete made, increasing local content opportunities
4) Most turbines have an energy payback of less than 6 months and a CO2 payback of 6 months
5) Turbine foundations can be concrete made, increasing local content opportunities